Selected assignments and experience from our specialists’ previous roles. Each example describes a distinct assignment; client and project identities remain confidential.
01 / Offshore wind
Foundation installation
An EPCI package spanning foundation design, fabrication, transport and installation.
Work undertaken
Programme and causation analysis examined ground information, design interfaces and vessel windows. Baselines, progress updates and project records supported preparation of an extension-of-time and prolongation claim.
Planning · delay analysis · claims02 / Offshore wind
Array cables & foundation handovers
Cable installation across a large turbine array, including links to offshore substations.
Work undertaken
Baseline, progress and handover records were compared to assess changing access dates and installation sequences. The work supported extension-of-time submissions and assessment of installation and payment milestones.
Programme review · EOT · milestone assessment03 / Offshore wind
Array & export cable campaigns
A phased installation campaign covering array connections, export cables and shore interfaces.
Work undertaken
Programme analysis, vessel deployment records and daily reports were used to examine access, seabed preparation and campaign changes. Event chronologies and supporting records informed the preparation of time and cost claims.
Delay analysis · records review · claims strategy04 / Offshore wind
Electrical substation delivery
A package spanning design, manufacture, equipment installation and commissioning.
Work undertaken
Programme logic, sequencing, progress reporting and forecasts were reviewed. Rescheduling showed how recorded progress affected key milestones and whether the planned sequence was achievable.
Programme scrutiny · oversight · forecast review05 / Interconnectors
Converter-station interfaces
Building works at a major HVDC converter station, with linked design, procurement and construction activities.
Work undertaken
Supporting analysis for an independent delay report examined successive programmes and project records. It traced design and specification issues through the critical path and handover forecast.
Delay analysis · interface review · expert support06 / Interconnectors
Marine installation contracts
Offshore installation delivered through specialist subcontract and consortium arrangements.
Work undertaken
Pre-execution review and negotiation, followed by contract administration in delivery. Work included change assessment, notices and variation proposals, alongside consortium decision-making and approval controls.
Contract management · commercial review · governance